Question QA-TW-0012
MediumA can finish a job in 16 days and B in 12 days. They work on alternate days, starting with A. In how many days will the job be finished?
- A.
13 days
- B.
14 days
- C.
Show answer and explanation
Answer: D
Each 2-day pair does 1/16 + 1/12 = 7/48. After 6 pairs (12 days): 42/48 done, 6/48 = 1/8 left. Day 13 (A): 1/16 more, leaving 1/16. Day 14 (B) needs (1/16) ÷ (1/12) = 3/4 day. Total days.