Question QA-TW-0015
Medium20 men working 8 hours a day finish a job in 15 days. How many days will 24 men working 10 hours a day take?
- A.
8
- B.
12
- C.
Show answer and explanation
Answer: D
Work = 20 × 8 × 15 = 2400 man-hours. 2400 ÷ (24 × 10) = 10 days.