Question QA-TW-0065
HardA can finish a job in 9 days and B in 12 days. They work on alternate days, A starting. How long does the job take?
- A.
11 days
- B.
10 days
- C.
10½ days
- D.
10¼ days
Sign up free to see the answer and a step-by-step explanation.