Question QA-TW-0070
HardA and B can finish a job in 8 days, and with C's help in 6 days. How long would C take alone?
- A.
48 days
- B.
14 days
- C.
Sign up free to see the answer and a step-by-step explanation.
Popular companies
Prepare company by company
Hiring pattern, syllabus, past questions and mocks for each company.
All companiesPractice by subject
Time and Work question
A and B can finish a job in 8 days, and with C's help in 6 days. How long would C take alone?
48 days
14 days
Sign up free to see the answer and a step-by-step explanation.
12 days
24 days